Monday, March 12, 2012
Friday, March 9, 2012
Thursday, March 8, 2012
The roof, the roof, the roof is on fire!
We don't need no water let the...
Actually we do need water. It'll come from the fire hydrant across the street next to Regions Bank.
This morning they started unloading the light weight concrete mix
That will get mixed with what's in this truck
And pumped up to the roof by this contraption
On top of this styrofoam that will be placed carefully on the roof to create the the proper drainage pitch
All under the watchful eye of Olivia
Should look very different by tomorrow morning
Actually we do need water. It'll come from the fire hydrant across the street next to Regions Bank.
This morning they started unloading the light weight concrete mix
That will get mixed with what's in this truck
And pumped up to the roof by this contraption
On top of this styrofoam that will be placed carefully on the roof to create the the proper drainage pitch
All under the watchful eye of Olivia
Should look very different by tomorrow morning
Wednesday, March 7, 2012
Tuesday, March 6, 2012
Monday, March 5, 2012
Busy week and the anatomy of a wall
This week there will be a lot going on at the site. Thursday and Friday will have the light weight concrete (they make a "light" version) pour on the roof in preparation of the paver system that will bring the finished floor up 15". That said - there will be a lot of activity on property and a water hose crossing Margaret Street at the end of the week to help mix the concrete.
More significant to us is what will be happening on the Northeast corner of the building involving the skin of the building - the Arriscraft Stone. Originally, the building was designed to have architectural precast panels on the outside. Smooth, clean, modern and quick - these panels would be put up as huge moduals by enormous cranes - all in the same week. After some local and regional research, all the groups involved with the project couldn't find precast panels that made everyone happy. During those discussions a year ago, the building redesign dictated by the Overlay was in process and a win-win solution was found - the Arriscraft Stone.
Installed like brick, the 1 foot by 2 foot stone will take about 2 months to finish as the weight limits it to 2-3 courses per day maximum. The finished product will be better long term for the building at the same time fit the neighborhood a bit better. Each one weighs about 60 pounds.
Below is the beginning of the wall with the Prosoco R-Guard waterproofing system that includes several layers of liquid, fiberglass and copper membranes finished with a stainless steel edge.
More significant to us is what will be happening on the Northeast corner of the building involving the skin of the building - the Arriscraft Stone. Originally, the building was designed to have architectural precast panels on the outside. Smooth, clean, modern and quick - these panels would be put up as huge moduals by enormous cranes - all in the same week. After some local and regional research, all the groups involved with the project couldn't find precast panels that made everyone happy. During those discussions a year ago, the building redesign dictated by the Overlay was in process and a win-win solution was found - the Arriscraft Stone.
Installed like brick, the 1 foot by 2 foot stone will take about 2 months to finish as the weight limits it to 2-3 courses per day maximum. The finished product will be better long term for the building at the same time fit the neighborhood a bit better. Each one weighs about 60 pounds.
Below is the beginning of the wall with the Prosoco R-Guard waterproofing system that includes several layers of liquid, fiberglass and copper membranes finished with a stainless steel edge.
Friday, March 2, 2012
Thursday, March 1, 2012
Core Boring for Beer
All floors in the building have long since been poured, but adjustments to the slabs continue. Carlos
has been core boring holes in the slabs all over the place to accommodate the conduit that will carry electricity, gas, water, waste, rain water and all sorts of things.
However, I would argue the MOST important core bore just happened:
Very soon, this hole will have 6" conduit that carries beer from the walk in cooler on the first floor to the rooftop patio! My Intuition tells me it will be good beer.
I'd trade this
for a Honey Badger any day!
has been core boring holes in the slabs all over the place to accommodate the conduit that will carry electricity, gas, water, waste, rain water and all sorts of things.
However, I would argue the MOST important core bore just happened:
Very soon, this hole will have 6" conduit that carries beer from the walk in cooler on the first floor to the rooftop patio! My Intuition tells me it will be good beer.
I'd trade this
for a Honey Badger any day!
Subscribe to: